STAGE 01Why a line RFQ is not a product RFQ
The unit of comparison is a scope, not a model number.
| LEDGER LINE | FIELD THE BUYER STATES | WHY IT GOES IN THE FILE |
|---|---|---|
| R01 / Product | Raw material condition and the finished format that leaves the line. | A model name without these two fields lets each workshop assume a different product. |
| R02 / Stages | Which process stages are in scope and where each one starts and ends. | Stage boundaries decide who owns the transfer between two machines. |
| R03 / Output | A planning band and the operating window the plant actually runs. | Include cleaning and changeover time so a quoted scope is not based on a different working day. |
| R04 / Utilities | Connection conditions at the machine interface, stated by the site engineer. | Availability elsewhere in the building is not a connection point. The utility interface checklist. |
| R05 / Materials | Contact-surface, seal and finish fields per assembly, not one blanket phrase. | Small parts drive maintenance reorders. The material record pack. |
| R06 / Records | Which build, test and cleaning records the supplier must supply. | A record is useful only when it names the equipment identifier and brief revision. |
The most common failure is a set of quotations that look similar but describe different lines. One includes the infeed conveyor, another assumes the buyer's existing conveyor; one includes a control panel, another prices only a mechanical frame. Writing the six lines above once and attaching the same sheet to every enquiry removes that ambiguity. A BOM comparison worksheet is a practical companion, and a wholesale line sheet keeps the commercial wording consistent across offers.
STAGE 02Raw material and finished format
Two fields that should never be paraphrased between versions.
Keep the exact wording of these fields fixed across the quotation, the technical agreement and the final equipment list. A short name on the quote and a longer description on the drawing creates the same mismatch that a document file is meant to prevent. A custom specification sheet is the usual template, and a private-label product brief shows how a consumer format is described in another category.
STAGE 03Output band and operating window
A planning figure is a field, not a performance promise.
STAGE 04Utility and site conditions
Connection points belong in the RFQ, not in an installation surprise.
STAGE 05Inclusions, exclusions and how offers are compared
The comparison table is only as good as the exclusions column.
| LEDGER LINE | FIELD THE BUYER STATES | WHY IT GOES IN THE FILE |
|---|---|---|
| Included | Each machine, transfer, control panel, guard and document named in the offer. | Write the same equipment description on every offer so the rows line up. |
| Excluded | Site works, connection hardware, installation, consumables and anything the buyer provides. | An unpriced exclusion is the most common source of a later change request. |
| Evidence | Which datasheet, drawing, record or acceptance note supports each row. | Evidence should name the brief revision it belongs to. Acceptance and change control. |
Once the three columns are filled, comparing offers becomes a reading exercise rather than a negotiation about what was meant. The same structure is used in a warehouse equipment RFQ worksheet and in a project BOM sourcing note, which is why a buyer who has used one of those pages will recognise this file.
STAGE 06Where the worksheet lives
One owner, one folder, one version at a time.
STAGE 07Questions buyers ask before the line brief is released
What is the minimum I can send to start a line RFQ?
Raw material condition, finished format, the process stages in scope, a planning output band and the site utility connection fields. A specification sheet gives the field layout.
Do you fill in the engineering values for me?
No. Values, standards and acceptance criteria come from you, your engineer and your appointed agent. We coordinate the file so every workshop quotes the same scope. Supplier verification explains the wider checks.
Why is an exclusions column so important?
Because an unpriced exclusion becomes a change request after the order is placed. A BOM comparison sheet shows how to keep the rows aligned across offers.
Should the RFQ mention certifications?
State which document fields your market requires and who supplies them, but leave applicability and standards to your agent. A document map shows the field structure used for other destinations.
Can one worksheet cover several workshops?
Yes. That is its purpose. The consolidation note explains how the same equipment descriptions then flow into one manifest.
Where do I put a revised output band?
In a new worksheet revision with an owner and an approval record. Sample approval gates and change control describe the discipline.