FAT, SAT and Change Control For Food Processing Equipment

HYGIENE FLOW BOARDFOOD PLANT FILE / STAGE 05PROCESS STAGES, NOT A SCHEDULEWhatsApp +86 186 7676 3055info@cinosourcing.com
CONTACT
SURFACE
GRADE BY ENGINEER
STAGE 05
TEST RECORD / REVISION BOARD
FAT, SAT and Change Control For Food Processing Equipment
For wholesale and project buyers, FAT and SAT are two acceptance records for the same line, and a file that treats them as separate paperwork loses the thread between them. The factory test shows what was observed before equipment leaves a workshop; the site acceptance shows what was observed after installation, when the utility connections, the upstream and downstream interfaces and the operator environment are real. This note sets out who writes each record, which evidence belongs in it, and how a parameter or part change after sign-off is kept visible. The RFQ worksheet defines the scope that the tests are run against, and the material record pack defines the documents that travel with it.
OPEN THE LINE FILE WITH
Product and raw-material list, process stages, target output band, site utility conditions, product-contact material fields, and the spare lines you expect to reorder. One brief, one equipment schedule, one load plan.
+86 186 7676 3055
info@cinosourcing.com
P01
P02
P03
P04
P05
P06
S1INTAKE
S2PREP
S3THERMAL
S4FILL
S5PACK
S6HOLD

STAGE 01Two acceptance records, one file

The second record should be able to refer back to the first.

Shared fields on an acceptance record
LOT REF
BRIEF REV
EQUIPMENT ID
CARTON REF
RECORD OWNER
Equipment ID
The identifier that links the machine to the brief revision and its datasheet.
Scope reference
Which section of the approved RFQ scope the observation belongs to.
Parameter set
The stored settings in use during the observation, named by revision.
Evidence list
Dated images, readings and observations the buyer asked to be kept.
Sign-off
Who reviewed the record and where the review is filed. Inspection scope.
· · · · · · · · · · · · · · · · · · · · · · · · · · · · · · · · · · · · · · · ·
The ticket is a record structure. It contains no acceptance values, no output figures and no delivery timetable.

A site acceptance record that cannot name the factory test it follows is hard to interpret. If a behaviour changes between the two, the file should show whether the scope, the parameter set, the utility connection or the installation changed. That is why the equipment identifier and the scope reference are shared fields rather than separate paperwork. A specification sheet is the usual home of the scope, and an inspection report structure from another category shows the same evidence discipline.

STAGE 02What the factory test should prove

Agree the observation list before anyone runs a machine.

Three columns for a factory-test plan
LEDGER LINE FIELD THE BUYER STATES WHY IT GOES IN THE FILE
Observation What the buyer wants to see: assembly state, run behaviour, cleaning access, interface signals, record output. Write observations, not performance claims, and name the scope line each one belongs to.
Material What representative product or test condition the buyer will provide, including a difficult case where the product varies. Testing only the easiest condition gives a weak basis for a line decision.
Evidence Which dated images, readings, parameter printouts and identifiers are kept, and who files them. Evidence should be legible and tied to the equipment identifier. First-article inspection.
Before a factory test is scheduled
Scope
The approved RFQ revision is attached, including exclusions.
Sample
Representative material and the conditions that matter are agreed in writing.
Measurements
The observation list names what will be recorded, not just whether the machine looks right.
Utilities
The test conditions at the workshop are described by the supplier and noted in the record. Utility interface checklist.
Change rule
Everyone knows how a deviation found during the test is recorded and approved.

STAGE 03What the site acceptance should prove

The line now has real connections and real neighbours.

Three record layers at site acceptance
REV A
Infeed and discharge heights, transfer widths and signal behaviour with the actual adjacent machines.
REV B
Connection conditions, drainage, ventilation and operator access as installed. Utility interface checklist.
REV C
Changeover steps, cleaning access and record output under the plant's own routine, observed by the buyer's team.
These are record layers. Site acceptance is not a delivery milestone and does not imply a commissioning window.

Most differences between a factory test and a site acceptance are interface differences, not equipment defects. A filler that behaved correctly alone may behave differently when the upstream conveyor stops and the downstream cartoner pauses. Recording the buffer rule and the signal behaviour at site acceptance keeps that distinction visible. The conveying and handling family owns those interface fields.

STAGE 04Parameter and firmware versions

A parameter change without a revision is an invisible engineering change.

Version risks and the control that contains them
MISMATCH IN THE FILE
CONTROL BEFORE RELEASE
A stored setting is adjusted during a test and nobody writes it down.
Record the parameter set by revision before and after the observation.
A control update is installed after sign-off with no record.
Treat it as a change request with an owner and an updated acceptance note.
Two machines carry the same model name but different parameter sets.
Give each its equipment identifier and keep the sets in one register.
A spare part is fitted from a different revision.
Record the substitution against the machine identifier. Material records.

The general rule is already documented on this site in engineering change control and sample approval and change control. A food line adds one complication: cleaning and changeover steps are also stored as settings in some plants, so those should sit in the same register as the machine parameters.

STAGE 05Spare parts and service records

An acceptance file should already describe the first reorder.

Three columns for a service record
LEDGER LINE FIELD THE BUYER STATES WHY IT GOES IN THE FILE
Part The reorderable reference and the assembly it belongs to. A description by appearance is not a part reference.
Revision The machine identifier and brief revision the part was approved under. This is what lets a later reorder match the installed machine.
History The dated replacement or repair note and the person who filed it. A service history is only useful when it can be retrieved against one machine.

A service record and a spare list should use the same references. The packing line spare kit and repeat-order spare planning show how those references are kept alive across a replenishment cycle, while the consolidation note explains how the first spare lines travel with the equipment load.

STAGE 06Who owns the file after sign-off

One owner replaces every previous version.

Published notes behind an acceptance file
Cluster pillar
Put the food plant equipment pillar in the same folder as the equipment list.
Category index
The field note that buyers usually attach here is the food equipment category index.
RFQ scope
Keep the line RFQ specification sheet beside the line layout in one shared file.
Utility fields
A longer working note on this interface sits in the utility interface checklist.
Material pack
Cross-check the specification against the material and hygiene document pack before the order is released.
Load plan
The same wording rule is used in multi-supplier consolidation and spares.
Inspection
Add pre-shipment inspection service to the RFQ attachment list for this stage.
Test plan
For the wider equipment family, see an inspection and test plan.
Sample gate
The checklist version of this field is sample approval and change control.
Change rule
The per-market file keeps engineering change control separate from the machine record.
Acceptance criteria, standards and approvals are set by the buyer and their engineer. This note describes the file that holds their evidence.

STAGE 07Questions buyers ask before the line brief is released

What is the difference between FAT and SAT on a food line?

FAT is the record of what was observed at the workshop before dispatch; SAT is the record of what was observed at the plant with real utilities and adjacent machines. Both should share one equipment identifier.

Do you set the acceptance criteria?

No. The buyer and their engineer write the observation list and the acceptance values. The RFQ worksheet is where the scope is defined.

Should representative product be used in a factory test?

That is a decision for your team, and a difficult case is often more informative than an easy one. A first-article inspection note describes the evidence structure.

How do we handle a control change after sign-off?

As a controlled revision with an owner, an updated parameter set and a note in the acceptance file. Engineering change control is the general method.

Are these records compliance certificates?

No. They are the buyer's own acceptance records. Applicability, standards and approvals remain with you and your appointed agent.

Where do spare part references come from?

From the original brief. The consolidation note explains how the first spare lines travel, and the replenishment kit shows the reorder view.

Send the line brief before you send the order
Process stages, product-contact material fields, utility connection conditions, upstream and downstream interfaces, the document set your market requires, and the spare lines for the next replenishment are enough to start. WhatsApp +86 186 7676 3055 · info@cinosourcing.com
HYGIENE FLOW BOARD / LINE FILEOne equipment schedule, one matching record set, one consolidated load.WhatsApp +86 186 7676 3055info@cinosourcing.com