The Component Brief: Eight Fields Before the RFQ Goes Out

THE COMPONENT BRIEF
Eight fields before the RFQ goes out

A controlled RFQ sends the same revision and the same commercial assumptions to every shortlisted supplier. If one factory quotes a different material or leaves out an inspection report, the two numbers are not comparable. These are the fields we ask for before anything is priced.

FIELD 01
Drawing revision
The current revision, not the one from the last order. Note any approved changes that are not yet on the drawing.
FIELD 02
3D model
Where relevant, plus the format your engineering team can review without a conversion argument.
FIELD 03
Material and finish
Grade, condition, surface finish and any coating requirement written as an acceptance criterion.
FIELD 04
Tolerances
Critical characteristics called out explicitly, with the measurement method and the standard named in your brief.
FIELD 05
Volume and batch sizes
Annual volume and the batch scenarios the price should be quoted against.
FIELD 06
Inspection and certificates
The dimensional report, material certificates and process records your program requires.
FIELD 07
Packaging and delivery point
Protection, separators, labels, batch identification and where the goods need to arrive.
FIELD 08
Change control
Which changes to material, process, tooling, site or sub-suppliers need written approval.
One revision, one set of assumptions, every supplier
We send the released package to each shortlisted factory in parallel, collect the exceptions they declare, and put the responses into one written comparison. The RFQ checklist is the starting point.

Running the RFQ in parallel matters as much as the fields themselves. When suppliers quote against the same revision at the same time, an exception is visible while the design can still change — a tolerance that opens the supplier pool, a substitute material with better availability, or a line that should have a second source. Sequential quoting hides those signals until the schedule is already fixed.

What belongs in the comparison

Unit price
Tooling
Quantity basis
Payment terms
Inspection scope
Packaging
Certificates
Delivery point

Normalising these fields matters more than the headline number. Landed cost on CNC parts explains why a lower unit price can be the more expensive route once tooling, inspection and freight are aligned.

The boundary we work to

We are a sourcing agent, not a manufacturer. We do not own a factory, do not issue quality-system certificates, and do not certify parts or processes. Those belong to the factory that makes the goods. We work to the released data package in your brief, check that a supplier’s documents cover the intended site, process and revision, and keep the records on file with the order.

Short answers

What if a field is still open?

Mark it as open in the brief rather than letting a factory fill it in. An assumption about material or pack size changes both the price and the documents, and a quote built on it cannot be audited later.

Can we use our own RFQ template?

Yes. Send it as the released package and we will work to it. What matters is that every supplier receives the same revision and the same commercial assumptions.

Do you issue the certificates we ask for?

No. Those come from the factory that makes the part. We check that the document covers the intended site, process and revision, and keep it on file with the order.

Send the released package in one file

We reply with verified factory options and a written, itemised all-in quote. See the full sourcing services.

Request a Component Quote →Chat on WhatsApp →

Leave a Comment

Your email address will not be published. Required fields are marked *