Sheet Metal Stamping Quote: The Specification Pack to Send

We are a Shenzhen-based sourcing agent and freight forwarder, working on the buyer side. We are not a stamping factory. We coordinate factories, tooling, inspection and shipping for buyers.

If three factories quote three different parts, the cheapest quote is usually the one that left something out.
— Why the brief comes first

A sheet metal stamping service can only give you a comparable price when every supplier is quoting against the same specification. The most common reason quotes differ by 40% is not factory efficiency — it is that the buyer left one of the fields below unspecified, and each factory made a different assumption.

The specification pack: fields you must freeze

Six fields that must be identical in every RFQ
Material
Grade + temper
Thickness
mm or gauge
Tolerance
Critical dims
Burr
Direction + limit
Surface
Finish + coating
Quantity
Per order + annual

Start with the drawing. Our product specification sheet guide covers the general structure; this guide focuses on the fields that move a stamped-part price.

1. Material: grade, not just “steel”

“Stainless steel” is not a specification. 304 and 316 behave differently in forming and cost differently. Cold-rolled, galvanised and spring steel each price differently. Write the grade and, where it matters, the temper or hardness. For a reference on thickness callouts, see the gauge chart.

2. Thickness: settle mm vs gauge

A gauge number means different thicknesses in different standards. If you specify 16 gauge, state which standard. Better: give a decimal thickness in mm. This single field causes more re-quotes than any other.

3. Tolerance: only where it matters

Tight tolerance on every dimension inflates the tool and the inspection time. Mark the two or three dimensions that actually matter for assembly and leave the rest at a commercial tolerance. The tolerance guide explains the general-tolerance principle, which applies here too.

4. Burr direction and edge condition

Stamping leaves a burr. Which side it is on, and how large it may be, affects the die design and whether a deburring operation is needed. If the part mates to another component, say which face must be burr-free.

5. Surface and secondary operations

Plating, powder coating, anodising, tapping, riveting or heat treatment are separate cost lines. List them explicitly rather than assuming they are included. Use the chips below as a checklist when you write the RFQ.

Common secondary operations

DeburrTumble / vibratoryZinc platePowder coatAnodisePassivateTappingRivetingWeldingHeat treat

6. Quantity: per order and annual

Tooling amortisation and piece price both depend on volume. Give the quantity for the first order, the expected reorder quantity, and the annual total. A supplier quoting 100 pieces and one quoting 10,000 are answering different questions.

Putting it into one comparable table

Line item Why it must be shown separately
Material + thickness So grade and gauge substitutions are visible
Die / tooling Buyout vs amortised vs included — see the tooling guide
Piece price by tier 100 / 1,000 / 10,000 pieces, so break-even is visible
Secondary operations Each operation as its own line, not bundled
Inspection + first article Whether FAI and reports are included
Packing + freight So landed cost can be compared — see landed cost

This is the same discipline as our CNC RFQ checklist, applied to stampings. Once the table is filled, the cheapest quote is the one that genuinely cost less — not the one that quoted less work.

The questions a factory will ask you back

A good supplier replies with questions, not just a number. Expect them to ask about the mating part, the annual volume, whether the part is formed or flat, and which surface will be visible. Being ready for these questions shortens the quote cycle and reduces re-quotes.

1
Is it flat or formed?
Formed parts need bend allowances and may need a different die approach.
2
What is the annual volume?
This decides whether tooling is amortised or charged as a buyout.
3
Which face is visible?
Cosmetic requirements change the deburring and finishing steps.
4
What does it mate with?
Assembly context decides which tolerances are actually critical.

A note on tooling in the quote

If a quote includes a die, ask whether the figure is a buyout, an amortisation over a stated quantity, or a loan tool. These are different commercial arrangements and they change what you own. The tooling ownership guide explains each one.

Frequently asked questions

QWhat is the minimum to get a stamping quote?
A 2D drawing with material, thickness, tolerance and at least one quantity. Samples help, but a drawing with dimensions is what makes the price comparable.
QWhy did two factories quote such different prices?
Usually one of the six fields was undefined — most often material grade, thickness standard or whether secondary operations are included.
QShould I send the same RFQ to several factories?
Yes, provided the specification pack is identical. That is the only way the quotes mean anything.
QDo I need a 3D file?
Not always. A clear 2D drawing is enough for many flat stampings; 3D helps for formed parts.
QWho owns the die after I pay for it?
State it in the purchase order. Our tooling ownership guide covers the options.
QCan you small-run stampings be economical?
Yes when consolidated. See consolidating metal parts.