How a project order differs from a restock
A restock repeats a known product. A project order often contains dozens of unrelated lines from different factories, each with a specification, a quantity, a marking requirement and a place in the installation sequence. The buyer is judged on whether the whole site works on handover day, not on the unit price of any single line.
That is why the first question is never “what does it cost” but “what exactly has to arrive, in what condition, with which documents and spares”. Our RFQ checklist and quote cost breakdown show the same discipline applied to custom-built parts.
What belongs in the RFQ
| Line | What to state | Why it matters |
|---|---|---|
| Item and model | Exact model, material, dimensions, rating, finish and the standard it must meet | The model on the quote, the label and the documents must be the same |
| Quantity and unit | Pieces, sets, cartons and any installation or assembly quantity | Prevents short deliveries that are expensive to correct |
| Electrical and markings | Supply voltage, frequency, plug type, label language and warning text | A unit configured for another market can be unusable on site |
| Documents | Commercial papers, origin evidence, permits or treatment marks required locally | Belongs in the purchase order, not in a later email |
| Packing and delivery | Carton strength, palletisation, humidity protection, unloading method and gateway port | Long routes and repeated handling |
| Acceptance | Who signs off, against which sample or specification, and what happens on failure | Makes inspection meaningful rather than decorative |
Many categories, one shipment
Project orders are where consolidation earns its keep. We receive each factory’s goods at our Shenzhen warehouse, check them against their purchase orders, photograph them, and load one container with one consistent document set. The alternative — several small shipments arriving on different rotations — is how handover dates slip. How consolidation works.
Spares, consumables and warranty
Write the spare-parts list, consumables, warranty period, exclusions and claim process into the purchase order. For equipment, ask which parts are expected to wear, which are included in the first shipment and how replacements will be shipped. A slightly higher first order that includes the right spares is usually cheaper than an emergency air freight later.
Inspection and the document pack
A commercial pre-shipment inspection checks your order against your specification. It is not a substitute for any destination-market approval your product needs — confirm those requirements with your broker before production. How we verify a factory.
A project order checklist
- Every line has a model, quantity, rating, marking and acceptance criterion
- Gateway port, delivery date and installation sequence agreed in writing
- Spare parts, consumables and warranty wording included in the purchase order
- Document, permit and treatment requirements confirmed with the local broker
- Consolidation cut-off date, inspection and loading photographs scheduled