A first article inspection on a China order answers one narrow question: do the first units produced under the real process conform to the released specification? It is not a pre-shipment inspection, which checks a finished batch, and it is not a sample approval, which decides what the standard should be. For custom orders from China it is the gate between a working prototype and a repeatable production run, and it is the gate most often skipped when a project is behind schedule. This guide sets out the records to request, how a drawing is ballooned, when a partial re-check is enough, and who signs the release. We are a sourcing, QC and freight partner, not a factory and not a test laboratory.
The short answer: what to request before the run starts
Request a traceable first article report, not a certificate-shaped summary. It should name the part number and drawing revision, the change identifier where one triggered the check, the lot or serial numbers, the process or tool identification, the equipment used and a measured result for each ballooned characteristic. Add the input-side evidence too: the released BOM, the approved vendor list and material identification for critical parts. A dimensional report can be perfect while the material grade is wrong, and that failure only appears in service. Finally, name the person on the buyer’s side who signs the release from the frozen file, and keep the outcome with the final inspection standard and the carton data.
Which gate answers which question
| Gate | Question it answers | Evidence produced |
|---|---|---|
| Sample approval | What should the finished product be? | Signed golden sample, approval sheet, frozen specification |
| First article inspection | Can the real process make that product, right now? | Ballooned drawing results, BOM sync, material ID, process settings, FAI report |
| In-process / DUPRO | Is the run staying inside the standard? | In-process checks, deviation records, corrective actions |
| Pre-shipment inspection | Does the finished batch conform before balance payment? | Quantity, workmanship, packing, labels, carton marks against the master |
| Reorder re-check | Does the master still describe what we are buying? | Revision re-check, retained references, deviation history |
The first article inspection sequence
The output is a decision, not a folder of measurements. If nobody can say whether the run is released, the gate has not been held.
Drawing, BOM, specification, artwork, ECN history and the signed golden sample must all carry the same revision. A mismatch here invalidates every measurement that follows. One master file holder prevents this.
Number each characteristic to be verified and define the method, equipment and acceptance criterion for it. Mark only what matters for form, fit, function, safety or appearance; general tolerance covers the rest.
Check part numbers, specification descriptions, units and revision against incoming parts, and confirm the approved vendor list has not drifted. Record material grade evidence where the design makes it critical. Unit conversion errors belong in this check.
Record measured values against each ballooned characteristic, the equipment used, the lot or serial, and the process or tool identification. Include function or assembly checks where a dimension alone cannot predict behaviour. Capability verification supports this step.
Issue a written outcome with the revision, ECN ID and any accepted deviations. Where a change affects form, fit, function, process or source, a full or delta FAI is required before the run resumes. Pre-shipment inspection then checks the whole batch.
Three findings that should stop a run
These are the failure patterns that a visual check will not catch and that a finished batch inspection is too late to fix cheaply.
An approved ECN never reached the production BOM, so old and new parts are both in use. Quarantine superseded stock and re-issue the revision before measuring anything. Change control is the companion guide.
A component looks identical on paper but comes from a source outside the approved vendor list. Compare the AVL against every BOM line, not just the description. Factory verification covers the supplier side.
The first articles came from a different tool, material lot or finishing line than the signed sample. Record the tool and process ID and require the intended route before release. Process capability varies by route.
What to actually request from the supplier
Ask for a report that is traceable, not a certificate-shaped summary. It should name the part number and drawing revision, the ECN or ECO identifier where a change triggered the check, the lot or serial numbers, the process settings, the equipment used, and a measured result for each ballooned characteristic. Photographs of the first articles and of the setup are useful supporting evidence. Where a qualified laboratory or standards-based verification is required by the destination market, confirm that separately with a qualified compliance body; we do not issue test reports and do not certify products.
Ask also for the input-side evidence: the released BOM, the approved vendor list and material identification for critical parts. A dimensional report can be perfect while the material grade is wrong, and the resulting failure only appears in service. For machined and formed parts, the RFQ checklist and landed cost work show why grade and process callouts should be written before the first article exists, not reconstructed afterwards.
Finally, decide who signs. On the buyer’s side the release should be a named person working from the frozen file, not an automatic consequence of receiving a report. Keep the FAI outcome in the same submittal index as the approval sheet, the artwork revision and the carton data, because multi-factory consolidation and freight planning will otherwise be built on an older description. Repeat wholesale programmes should re-open that file at every reorder.
Full FAI or delta FAI?
- A new part, a new supplier, a new tool, or an extensive design change.
- A long gap since the last production run, or a moved production location.
- Verify every ballooned characteristic and re-issue the control plan.
- Usually paired with factory verification and a new golden sample decision.
- A defined change affecting a limited set of characteristics.
- Verify the affected characteristics plus anything the change could influence.
- Tie the report to the ECN ID, part number and new revision; state effectivity.
- Route the decision through the master file and the final inspection standard.
This guide describes a buyer-side control process, not certification, legal or engineering advice. We are not a factory and do not issue test reports. Where standards-based verification, regulated testing or formal FAI requirements apply, confirm the scope with a qualified compliance body, licensed broker or the relevant standards owner.
Frequently asked questions
Is a first article inspection the same as pre-shipment inspection?
No. FAI verifies the first units from the real process against the released specification; pre-shipment inspection checks the whole finished batch before balance payment. See pre-shipment inspection.
When is a delta FAI enough?
When a written change affects a defined, limited set of characteristics and the rest of the process is unchanged. The report must still be tied to the ECN ID and the new revision.
What is a ballooned drawing?
A drawing with each characteristic to be verified numbered, so every measured result can be traced to a specific requirement and method. Mark only the characteristics that matter; use a general tolerance for the rest.
Do you issue the FAI report or test certificates?
No. We coordinate the buyer-side control, hold the master file and review the evidence. We do not certify products and do not issue test reports; where formal verification is required, use a qualified body.
Who signs the release to continue production?
A named person on the buyer’s side, working from the frozen revision and the written outcome. Our procurement desk keeps that decision with the approval sheet, artwork and carton data.
Send the specification and we will build the quote around it.
Include the product or drawing, the destination market, your quantity breaks, the changes you want made, and the documents your channel requires. We work as your sourcing, quality control and freight partner in China; we are not a factory and do not issue test reports or certificates.
WhatsApp / Phone: +86 186 7676 3055
Email: info@cinosourcing.com
Or use the contact form.
Part of our Custom Product Sourcing From China hub: specification control, tooling, sampling, inspection and shipping for wholesale, OEM and project orders.